Wednesday, January 5, 2022

Building Update January 5, 2022

 Happy New Year Pheasants!!

Quick building update.  The new elementary building is starting to take serious shape.  The walls are up, the top floor is on and the roof is being poured as we speak.  The progress Fiegen Constructing is making every day is tremendous.  We are grateful and happy to be working with such dedicated craftsman as they work diligently on our facility.  We are easily on schedule at this time, thanks to great weather and dedicated workers on site.  The next steps in the process is exterior bricks will be added next week, and continued inside infrastructure.  As soon as it's safe, we plan on offering tours, most likely as the weather warms this spring.  Until then, stay tuned.  #parkerpride